Back to Projects

Donald and Tarnagulla Microgrid Feasibility Study

Rural and regional communities tend to be at the end of the grid or have long distribution lines, leading to quality deterioration of the electricity supply. These communities and their businesses are seeking a balance of reliable, sustainable and low-cost electricity tailored to their needs.

Communities are becoming progressively aware of alternative energy supplies to either enhance their existing supply or to explore alternative supply options, such as microgrids. Distribution Businesses (DBs) often receive queries on exploring microgrid opportunities for their communities. Several community groups across the Loddon-Mallee area have sought to investigate whether microgrids are a better energy solution for their electricity needs.

Microgrids are becoming increasingly commercially feasible in Australia under certain circumstances, in part driven by technical and cost improvements. However, their analysis is complex and balancing the needs, benefits and costs across the varied stakeholder groups is a challenge. There is also lack of understanding on microgrid reliability, benefits, operation, ownership and the governing market rules.

The project balanced the technical, cultural and social elements of understanding the feasibility of microgrids. Key project milestones included community engagement, area hosting capacity assessment, concentrated generation and storage impact, network assessment, islanding design and cost analysis, microgrid impact study, stakeholder impact investigation, economic and risk assessment, microgrid assessment tool development and recommendations to regulators. The multi-year project concluded in 2023.

This study was supported by the Department of Industry, Science, Energy and Resources and C4NET.

Events

Milestones

The study was divided into 12 different projects.

1. Project Commencement

Partners

C4NET

CVGA

Summary

Project start – stakeholder launch event.

Timeline

Status:
Complete ✓

Start Date:
14/09/2021

Energy Future Forum Presentation

Download

2. Community Engagement

Partners

Swinburne University

CVGA

Summary

A mix of surveys, interviews, community meetings and information updates for energy consumers impacted to determine energy needs, appeal of various trade-offs, what changes to current supply could be accepted and behavioural change elements . Willingness to participate will be measured against factors such as energy literacy, values and aspirations.

A series of energy literacy videos can be viewed here –  https://www.cvga.org.au/energy-literacy.html

Timeline

Status:
Complete ✓

Developing Energy Literacies for Meaningful Community Engagement

Download

3. Network Assessment

Partners

Powercor

Summary

Assess the current and forecast status of supply to Donald and Tarnagulla. This will include grid and customer characteristics, demand peak, volume, events impact, known constraints, and power quality analysis.

Timeline

Status:
Complete ✓

Network Assessment Report

Download

4. Area Hosting Capacity Assessment

Partners

RMIT University

Summary

For each town, model different hosting scenarios for self-generation including solar, diesel/gas gen-sets, storage and demand response options and network synchronous needs.

Timeline

Status:
Complete ✓

Area Hosting Capacity Assessment Presentation

Download

Area Hosting Capacity Assessment Final Report

Download

5. Islanding Design and Cost Analysis

Partners

Federation University

Summary

Defining the optimal location for islanding points, designing elements, the cost of doing so (hardware, installation and ongoing operational), and a network connection assessment.

Timeline

Status:
Complete ✓

Islanding Design and Cost Analysis Report

Download

Islanding Design and Cost Analysis Presentation Slides

Download

6. Stakeholder Impact Investigation

Partners

Swinburne University

Summary

Includes customer critical needs analysis and the microgrid’s ability to prioritise supply ranking if islanding occurs (eg hospital, life support premises, commercial/residential considerations), impact on business attractiveness, regulatory requirements for de-energising and re-energising.

Timeline

Status:
Complete ✓

Start Date:
01/10/2021

Stakeholder Impact Investigation Final Report Donald and Tarnagulla Microgrid Feasibility Study

Download

7. Microgrid Impact Study

Partners

University of Melbourne

Summary

Model microgrid impact (full-time, partial, and status quo), covering both the islanding component and its impact on the broader network.  This milestone considers event-driven microgrid appeal such as high bushfire danger days and how many critical event days are likely to occur, cost of covering them etc.

Timeline

Status:
Complete ✓

Start Date:
01/10/2021

Project 7. Microgrid Impact Study- Final Report Donald and Tarnagulla Microgrid Feasibility Study- The University of Melbourne

Download

8. Economic and Risk Assessment

Partners

University of Melbourne

Federation University

Summary

Includes analysis of the value potential created, investment required, alternatives (including network storage etc) and community effects (impact on all grid-users) and risks.

Timeline

Status:
Complete ✓

Start Date:
01/04/2022

Economic and Risk Assessment – Part I Final Report

Download

Economic and Risk Assessment – Part 2 Final Report

Download

9. Concentrated Generation Impact (Demonstration)

Partners

CVGA

Summary

Install up to 1 MW commercial rooftop and 500 kW solar systems in priority hosting areas. Customers/third party providers will invest but incentives will be designed to highly encourage participation. Any site will be subject to network permission to connect and customer acceptance.

Status:
Complete ✓

10. Concentrated Storage Impact (Demonstration)

Partners

CVGA

Summary

Install either network side or customer side batteries (with network operational control under certain conditions) co-located with solar above.

Status:
Complete ✓

11. Recommendations to Regulators

Partners

University of Melbourne

Summary

Report impacts of potential regulatory changes the study identifies to drive the economic, power and social outcomes sought.

Status:
Complete ✓

Start Date:
01/10/2022

Recommendations to Regulators on Microgrids

Download

12. Microgrid Assessment Tool Development

Partners

Deakin University

Summary

Develop a tool that would help any similar regional town understand how well-suited they are for microgrids from the analysis performed in this study.

Click Here for the Microgrid Assessment Tool

Status:
Complete ✓

Start Date:
01/10/2022

13. GWM Water - Donald Industrial Site Feasibility Assessment

Partners

Powercor

Summary

Analyse the GWM-Donald industrial park site relative to other sites in the Powercor network for microgrid implementation.

Status:
Complete ✓

Start Date:
18/10/2021

Microgrid opportunities identification

Download

Project Completion

Partners

C4NET

Summary

Final revision of microgrid design, economic and risk analysis, customer participation statistics and regulatory findings based on inputting final data from DER (generation and storage) sites. Final report compilation.

Status:
Complete ✓

Start Date:
30/04/2023

Microgrid Feasibility Study – Donald & Tarnagulla. Final Report

Download

Media & Resources

Final Report • September 2023

Microgrid Feasibility Study – Donald & Tarnagulla. Final Report

Report • June 2023

Developing Energy Literacies for Meaningful Community Engagement

Report • April 2023

Donald and Tarnagulla Microgrid Study: Recommendations to Regulators on Microgrids

Report • February 2023

Donald and Tarnagulla Microgrid Feasibility Study – Progress Report February 2023

Report • August 2022

Donald and Tarnagulla Microgrid Feasibility Study – Microgrid Impact Study

Report • August 2022

Donald and Tarnagulla Microgrid Feasibility Study – Microgrid opportunities identification

Report • August 2022

Donald and Tarnagulla Microgrid Feasibility Study – Stakeholder Impact Investigation

Report • August 2022

Donald and Tarnagulla Microgrid Feasibility Study – Progress Report August 2022

News article • February 2022

Powercor: Donald and Tarnagulla residents invited to have their say on the new energy future

News article • February 2022

The Irrigator: Tarnagulla, Donald microgrid feasibility study to look at town needs

News article • February 2022

The Standard: Tarnagulla, Donald microgrid feasibility study to look at town needs

News article • February 2022

Ararat Advertiser: Tarnagulla, Donald microgrid feasibility study to look at town needs

News article • February 2022

Bendigo Advertiser: Tarnagulla, Donald microgrid feasibility study to look at town needs

News article • February 2022

Renew Economy: Two Victorian towns could go off grid under new network proposal

News article • February 2022

ABC: Microgrids could become new energy solution for towns like Tarnagulla and Donald

Report • January 2022

Donald and Tarnagulla Microgrid Feasibility Study Progress Report

Return to Top